globenewswire.com · Nov 6, 2025
Minim Martap Project Update
Highlights Construction work ongoing on ore haulage access road, IRF and site access Locomotives delivery remains on schedule in first quarter 2026 Mining contractor has visited site confirming mobilisation schedule with mine development to commence in first quarter 2026 Project development timeline remains unchanged Project fully financed to Stage 1 production Incumbent President Paul Biya has been officially re-elected as the President of Cameroon PERTH, Australia, Nov. 06, 2025 (GLOBE NEWSWIRE) -- Canyon Resources Limited (ASX: CAY) (‘Canyon' or the ‘Company') is pleased to provide a project update for its Minim Martap bauxite project (‘Minim Martap' or ‘the Project') in Cameroon, following the confirmation of President Paul Biya's re-election. Despite reports of unrest in several Cameroon cities in the immediate aftermath of the election, Canyon has continued to progress its development of the Minim Martap project with minor delays to construction work in key areas.